Staples_web1
ear studio
Search

Waves Aquatic Centre Upgrade

By Dr Peter Gangemi - Mayor of The Hills Shire Council
Check out these drone shots showing the progress of the Waves Fitness and Aquatic Centre

As per the photos, the structural steelwork for Waves is substantially complete and the shape of the building is clearly visible. Current works on site include:

• Installing the gymnasium floor
• Warm water pool tiling, which is mostly complete
• Preparing the indoor lagoon pool for tiling
• Change room floor and wall tiling
• The installation of timber ceiling panels in the main lobby
• The construction of the clubhouses
More information and a timeline can be found on Council’s website at
Home Maintenance